S/N Project Name & Region Client Name State Year Duration Scope of Work Mode of Contract Status
1 Purchase of Critical Spares (Mechanical) Olorunsogo Generation Company Limited NDPHC Olorunsogo, Ogun State 2019 30 Days Procurement Main Completed
2 Purchase of Filter Sets ffor Ogorode (Sapele) Generation Company Limited NDPHC Sapele, Delta State 2019 30 Days Procurement Main Completed
3 Construction of 800m asphaltic road with concrete drainage at Oyo south East LGA. OYO STATE GOVERNMENT Ibadan, Oyo State 2019 8 Months Construction Main Completed
4 Construction of 6 Bedroom Country Home with Supporting Structures in Ibadan Private Client Ibadan, Oyo State 2019 16 Months Construction Main Completed
5 MMIS Headoffice renovation in Abuja Mar & Mor integarted services limited Abuja, FCT 2018 8 Months Construction Main Completed
6 Construction of 5 bedrrom modern house in Guzape, Abuja Mar & Mor integarted services limited Guzape, Abuja 2019 12 Months Engineering, Construction & Procuremnet Sub Contractor Completed
7 Purchase For Oil Mist Eliminator Filter Omotosho Generation Company Limited NDPHC Okitipupa, Ondo State 2019 30 Days Procurement Main Completed
8 Purchase of Instrumentation and Control (I&C) Critical Items for Ogorode Power Station NDPHC Ogorode, Edo State 2019 30 Days Procurement Main Completed
9 Purchase of Critical Instrumentation and Control (I&C) Items for Benin Generation Company Limited NDPHC Benin, Edo State 2020 30 Days Procurement Main Completed
10 Purchase of 40 Nos of Thrust Pads & 57 Nos of Oil Seal to Olorunsogo Generation Company Limited NDPHC Olorunsogo, Ogun State 2020 30 Days Procurement Sub Contractor Completed
11 Purchase of Oil Mist Eliminator Filter to Calabar Generation Company Limited NDPHC Calabar, Cross River State 2020 30 Days Procurement Main Completed
12 Purchase of Filter sets for Calabar Generation Company Limited NDPHC Calabar, Cross River State 2019 30 Days Procurement Main Completed
13 Purchase of 750 Mist Eliminator Filters to Benin Generation Company NDPHC Benin, Edo State 2019 30 Days Procurement Main Completed
14 Provision of Solar Powered Street Light in Selected Communities in the Nigeria Delta (Lot 1) NDDC Portharcourt, River State 2019 12 Months Procurement and Installation Main Ongoing
15 Provision of 1NO Motorised Borehole at Irogun - Olarunda Federal Ministry of Works and Housing Public Procurement Department (Housing Sector) Egbado South LGA, Ogun State 2020 3 Months Procurement, Installation & Construction Main Completed
16 Procurement of 48 pcs of thrust pads and 72 pcs of oil seals for Olorunsogo Power Plant NDPHC Olorunshogo, Ogun State 2021 6 Months Procurement Main Ongoing
17 Emergency procurment of maintenance spares for GT2-2 at Alaoji Power Plant NDPHC Aba, Abia State 2021 6 Months Procurement Main Ongoing
18 Production of 100 Road Mats Per State for 36 States and FCT FERMA 36 State + FCT 2021 3 Months Production Main Ongoing
19 Completion of Ongoing Electrification of Araba Idoko and Ofugolo In Dekina LGA Rural Electrification Agency Dekina LGA, Kogi State 2020 4 Weeks Electrical Instrumentation and Control Main Completed
20 Rehabilitation and Maintenance of Tinuoye Arulogun Ojoo Junction, Ibadan Oyo FERMA Ibadan, Oyo State 2020 6 Months Construction Sub Contractor Completed
21 Procurement for Crititcal Mechanical Spare Part at Olorunsogo Generation Company NDPHC Olorunsogo, Ogun State 2020 30 Days Procurement Sub Contractor Completed
22 Procurment of Spare Parts FPR Calabar Generation Company Limited NDPHC Calabar, Cross River 2020 30 Days Procurement Sub Contractor Completed